Downtown Blackstone Inc.
P.O. Box 417
Blackstone, VA 23824
434-292-3041

Email

Monthly Contractor's Meeting

MARCH 25th

Attendees:   D.B.I                                 Town of Blackstone  W.E. Bowman       B&B Consultants

                       Joe Allman                       Larry Palmore               Brendan Fagan       David Boaz

                       Lafayette Dickens                                                                                           Randy Jones

Project Status:

Work has begun on 105, 107, 120, and 118 West Broad Street

Schedule of Completion:

Substantial completion by Agreement is September 30, 2009.

Final completion by Agreement is October 30, 2009.

Application for Payment was reviewed and approved.

Change Order decreasing the scope of work by $218,861 was reviewed.

Town of Blackstone Comments

Use of ladders on the HL Jackson facade was questioned due to the risk of denting. Concrete plans for apartments and accessing the Housing program for upper level living units in the Borum properties was inquired about. Questions concerning parking and zoning requirements were raised. B&B consultant David Boaz committed to supply Mr. Palmore with a copy of South Hill's overlay area as a sample document to consider.

DBI Comments

The topic of replacing the clouded panes on the Coke building was discussed. Since this is not in the scope of work for the building, the expense would fall on the owner. Mr. Watkins' request to use Roberts Awning company was considered. Steel frames are indicated on the scope of work for Watkins Jewelers but not on the Borum's building. It was mentioned that they have requested them but Mr. Fagan suggested that the aluminum frames were preferable  for practical reasons to be explained to the property owner.

Francis Gilmore's request for a change to his scope of work was submitted and accepted by all parties present as reasonable. Mr. Palmore agreed based on the stipulation that the request go before the DBi review board first and then the Management team. Tommy Watkins' request to use Benjamin Moore Paint was approved.

The status of the Brown street side H.L. Jackson facade was questioned.

B&B Comments

Mr. Boaz presented a reasonably priced quotation from Perimeter Systems for a custom manufactured coping for the overhang that is attached to the Brown Street side of the H.L. Jackson building.  He further stated that we would have a copy of this pre-fitted aluminum product by the first of the week. This seemed to meet everyone's approval. No submittals had been received to date. Submittals are to be supplied by W.E. Bowman.

APRIL 22nd

Attendees:   D.B.I                                 Town of Blackstone  W.E. Bowman       B&B Consultants

                       Joe Allman                       Larry Palmore               Brendan Fagan       David Boaz

                       Lafayette Dickens          Jennifer Beck                  Ed Bowman             Randy Jones

                                                                                                                Joe VanValkenburg

Project Status:

Work has begun and near completion on the following buildings:

105, 120, 118, 107 103 and 110 West Broad Street

115-117, 119, and 114 South Main Street

Change order Status: No. 1 -$218,861 decrease (approved)

Town of Blackstone Comments

Any changes in scope of work on buildings must be approved by DBi, DHCD, and DHR

(Downtown Blackstone, Inc., Dept. Of Housing and Community Development and Dept. of Historic Resources)

New Business

Provide change order to Town so that it can be forwarded to Matt Fitzgerald

DBI Comments

Owners desire to have a steel framed awning on the Doswell property as opposed to aluminum was disclosed.

New Business

106 N. Main Street requested a cost estimate on a copper roof and wants to know if the roofline can be lowered below the window. It was stated that changing the shape of the awning would be costly. 108 N. Main Street was officially removed from the project and is to be added to Changeorder #2 as a deduct. 101 S. Main needs to reduce construction to a total of $20,000 ($10,000 per facade).

Contractor's comments

Contractor will have no issue with using Benjamin Moore paint as requested and will provide submittals.

New Business

Job schedule and overhead door was submitted along with changeorder #2. Contracdtor will price cost for gutter to be put on adjacent building of 111 W. Broad Street. Town request this be handled through the building owner and not the Town. 119 S. Main Street needs a price for replacing glass panel.

Engineer's comments

Needs to get submittlas, needs price for 111 N. Main St., review price on Cornice of Jackson Building, new price for canopy on Sheet 18 of Change order 2. Attach quotation for Epps Building.

New Business

B&B will review payment #3 and forward to Town. Owner of 120 E. Broad Street needs to meet with B&B to discuss their request for a modification of plan. B&B will proceed with Change order #2 and once it is signed by the contractor and the engineer they will forward it to the town.

May 27th

Attendees:   D.B.I                                 Town of Blackstone  W.E. Bowman       B&B Consultants

                       Joe Allman                       Larry Palmore               Brendan Fagan       David Boaz

                       Lafayette Dickens          Jennifer Beck                                                      Randy Jones

                                                                                                               

Project Status:

Work has begun and near completion on the following buildings:

105, 120, 116-118, 107 103 and 110 West Broad Street

115-117, 119, 114 and 116 South Main Street

113-115, 121, 112, 104, 100 and 110 N. Main Street

101, 103 E. Broad Street

Change order Status: No. 1 -$218,861 decrease (approved)

                                          No. 2 $26, 730 decrease has been submitted (reviewed prior to meeting and will be revised and resubmitted)

Application for Payment

#1 has been paid

#2 - #4 have not been paid

#5 submitted at meeting

Town of Blackstone Comments

No new comments

New Business

Payroll and labor standard from Contractor and subcontractor for Feb, March, and April must be provided. Payroll is required to be submitted weekly.

DBI Comments

New Business

Need copy of paint specifications from Engineer and a PDF of painting section to distribute to the Design Committee.

Contractor's comments

no new comments

Engineer's comments

No new comments

July 1st

Attendees:   D.B.I                                 Town of Blackstone  W.E. Bowman       B&B Consultants

                       Joe Allman                       Larry Palmore               Brendan Fagan       David Boaz

                       Lafayette Dickens          Jennifer Beck                                                      Randy Jones

                                                                                                               

Project Status:

Work has begun and near completion on the following buildings:

Substantially completed

105, 120, and 107 West Broad Street

119  South Main Street

121, 112, and 110 N. Main Street

Other work continues

116-118, 103 and 110 West Broad Street

115-117,114 and 116 South Main Street

113-115, 104, and 100 N. Main Street

101, 103 E. Broad Street

Change order Status: No. 1 -$218,861 decrease (approved)

                                          No. 2 $26, 730 decrease has been submitted (reviewed prior to meeting and will be revised and resubmitted- At the May meeting, contractor stated that his cost will need to be revised. Contractor was to forward revised cost to Engineeer so that change order No. 2 could be revised. Have not received this information as of yet)

Application for Payment

#1 and #2 has been paid

#3 - #4 have not been paid due to proper form not been submitted

#5 submitted at meeting

Town of Blackstone Comments

New Business

Payroll and labor standard from Contractor and subcontractor for Feb, March, and April must be provided. Payroll is required to be submitted weekly. Contractor cannot be paid until all subcontractors payrolls are properly filled out and submitted. Town will be audited in the next two weeks. it would be greatly appreciated if all required documents from contractro are submitted including those required for Application #1 and #2 which have already been paid.

Had an issue with the paint contractor about leading the building owners beyond the scope of painting specified. Performing artwork (i.e. fleur de lis, shells, raised elements on metal facades) was not the intent of the project; now, other building owners want this type of service.

DBI Comments

Handout was provided concerning owners request for changes from: Francis Gilmore, Tommy Watkins, Borum's Brown Street, and Doswell Building.

New Business

Owner of Coca-Cola building is checking on the correct green color designation. Once obtained, it will be forwarded to the contractor to revise the sign accordingly.

Contractor's comments

New Business

Primary contractor agreed that painter has created an issue. if this issue can not be resolved with Mr. Teefey, the painter will perform the work requested at no additional cost.

Engineer's comments

B&B will proceed with change order No. 2 and once signed by contractor and engineer will forward to town.

New Business

Brown street side will be submitted by July 2, 2009.

September 2nd

Attendees:   D.B.I                                 Town of Blackstone  W.E. Bowman       B&B Consultants

                       Joe Allman                       Larry Palmore               Brendan Fagan       David Boaz

                       Lafayette Dickens          Jennifer Beck                                                      Randy Jones

                                                                                                               

Project Status:

Work has begun and near completion on the following buildings:

Substantially completed

103, 105, 107, 109, 110, and 120 West Broad Street

119  South Main Street

121, and 112 N. Main Street

117 East Broad Street

Other work continues

116-118 West Broad Street

100, 108, 115,114 and 116 South Main Street

113-115, 104, and 100 N. Main Street

101, 103 113 E. Broad Street

Status Updates:

106 North Main out of program (to be completed by others)

108 North Main Street waiting on Notice to Proceed (DHR must approve)

120 E. Broad (waiting on approval of change in scope re: windows from DHR)

120 West Broad Street Facade B (waiting approval from DHR)

111 West Broad Street (out of contract-work to be done by owners per letter sent to Town)

110 South Main Street (price change to be reviewed and approved)

Change order Status: No. 1 -$218,861 decrease (approved)

                                          No. 2 $60,1 74 decrease and 17 day extension (approved)

Application for Payment

#1 through #3 have been paid

#4 to be paid today

#5 submitted should be paid within 3 weeks

#6 has been forwarded for approval

#7 submitted to the town at today's meeting

Town of Blackstone Comments

New Business

Town must collect escrow funds from 120 East Broad before work begins.

DBI Comments

New Business

List of business owners issues and concerns was discussed and solutions presented.

Contractor's comments

No New Business

Engineer's comments

New Business

Brown street side should have a determination from DHR  by Friday, September 4th.

Contractor submitted an itemized list of the cost estimation for work on orginial bid for 110 South Main for review, comment and approval

DBi set up meeting for Town and owner of 111 W. Broad Street regarding facade painting.

100 S. Main Street owners accepted the proposal from B&B for getting the scope below the $10,000 mark and chose a first and second choice for awnings and is now awaiting a price difference in order to decide.

Next meeting set for Wednesday, October 7th at 2pm

 

 

 

Back to the news page

 

"));